| Project and LSR-cell boundary | Intended part/application, included IMM, LSR injection unit, LDS, mold/cold runner, vacuum, automation, peripherals, site work, supplier work and explicit exclusions | Approved scope diagram and responsibility matrix naming every package and project owner |
|---|
| Part, application and acceptance owner | Controlled part/mold/application identities, quality and production questions, trial owner, disposition authority and unresolved use-specific requirements | Buyer-approved project basis without implying suitability, regulatory status or an achieved result |
|---|
| Injection molding machine identity | Exact proposed IMM, clamping unit, controller, software/option baseline, interfaces and responsible machine party | Configuration-specific machine record without implying a NEW ORIENTAL IMM LSR option or supply capability |
|---|
| LSR injection-unit identity | Proposed injection-unit architecture, controlled configuration/revision, interface points, thermal responsibilities and responsible supplier | Supplier configuration drawing and option/exclusion record; a generic LSR label is insufficient |
|---|
| LSR dosing-system identity and revision | Proposed LDS manufacturer, model/configuration, serial identity when assigned, controller/software revision, mapping identity and responsible supplier | Controlled supplier configuration without treating a product family, photo or companion-specification title as project proof |
|---|
| Exact material and A/B lot register | Material producer, exact grade, current SDS/TDS references, Component A and B identities, lot/expiry records when required and approved substitutions | Controlled material documents and project lot register; no formulation, ratio or processing value is supplied here |
|---|
| Additive and color register | Every proposed pigment, color or additive identity, supplier/grade, component relationship, approval owner and excluded stream | Buyer/material-supplier-approved component list without a fixed percentage, recipe or device selection |
|---|
| Material-balance and mixing basis | Supplier-defined balance method, required material relationships, target/actual semantics, deviations to evaluate and approval owner | Configuration- and material-specific basis; no universal ratio, tolerance, calibration or correction method |
|---|
| Container, follower and material-change boundary | Proposed pail/drum/container identities, follower or transfer equipment, segregation boundary, retained-material locations, change responsibility and access questions | Controlled package drawing and material-change evidence index without loading, drum-change, cleaning or purge instructions |
|---|
| Metering, mixing and mixing-point architecture | Supplier-defined pumping, metering and mixing topology; Component A/B/additive path; identified mixing point; included instruments; unsupported alternatives | Configuration drawing and functional description rather than a universal static/dynamic mixer or pump recommendation |
|---|
| Physical material path to injection unit | Controlled path from each material container through the included LDS/mixer to the injection-unit inlet, with isolation, support and handoff owners | Reconciled material-flow and arrangement drawings with as-installed identities |
|---|
| Cold-side and heated-mold thermal boundary | Which identified components require controlled cold-side or heated-mold treatment, measuring/control owners, interfaces and open material-supplier questions | Project thermal-responsibility diagram without a temperature, circulation, insulation or startup instruction |
|---|
| Mold, cold-runner and nozzle handoff | Identified mold entry, LSR cold-runner, nozzle/contact, vacuum and automation handoffs; drawing owners; included controls; explicit hot-runner exclusions | Controlled interface drawings and responsibility matrix showing that an LSR cold runner is not released by a thermoplastic hot-runner schedule |
|---|
| IMM-to-LDS cycle and synchronization path | Required cycle identities, initiating/receiving owners, ready/active/complete/inhibit/fault functions, proposed physical/data paths and exclusions | Approved functional matrix and configured observations without publishing a signal order, pinout, timing or motion sequence |
|---|
| OPC 40082-3 release and conformance scope | Selected EUROMAP 82.3 / OPC 40082-3 release, namespace/model version, common-type basis, proposed profile/facet/conformance units and extensions | Dated applicability and support matrix distinguishing mandatory, optional, vendor-specific and unsupported elements |
|---|
| Endpoint, read, write, method and hardwired split | Identified endpoint owner, proposed read/write/method families, business purpose, authorization owner, unsupported functions and separate hardwired/proprietary paths | Configuration-specific support/test matrix; no node list, address, port, credential, certificate or network design is published |
|---|
| Alarm, fault, reset and safety boundary | Required state/error meaning, source, display/record owner, acknowledgement/reset authority, product-disposition owner and safety-related exclusions | Approved semantic and safety-responsibility matrices; no alarm value, reset action, recovery method or safety validation is supplied |
|---|
| Utilities, layout, access and load ownership | Configuration-specific services, package loads, site connection points, arrangement, maintenance/material access, structural responsibility and dependencies | Supplier schedules and approved drawings without a fixed capacity, connection, mounting or installation instruction |
|---|
| Configured LSR FAT and SAT evidence | Identified machine/LDS/injection-unit/mold/material configurations, required states and records, witnesses, deviations, retest and closure owners | Approved project FAT/SAT references and dated observations under the separate acceptance programme |
|---|
| As-built handover, change control and revalidation | Final equipment/material identities, drawings, software/specification releases, mappings, accepted deviations, open assumptions, change owners and recheck triggers | Signed handover index and action register; unanswered capability, compatibility, value or evidence items remain open |
|---|