| Project and dryer-interface boundary | Included resin-drying function, dryer, bin/hopper, loaders and conveying handoffs, IMM feed-throat boundary, site work, supplier work and explicit exclusions | Approved scope and material-flow diagrams with a responsibility matrix for the material, dryer, conveyor, machine and site parties |
|---|
| Injection molding machine identity | Exact proposed IMM, injection unit, feed-throat/receiver relationship, controller, software/option baseline and responsible machine party | Configuration-specific machine record without implying a NEW ORIENTAL IMM dryer, drying or integration capability |
|---|
| Dryer, controller and software identity | Proposed dryer manufacturer, model/configuration, bin or hopper relationship, controller/software revision, options, serial identity when assigned and responsible supplier | Controlled supplier configuration and option/exclusion record; a family name, photograph or generic dryer label is insufficient |
|---|
| Exact material, color and regrind/PCR register | Material producer, exact grade, color/additive state, filler or reinforcement, approved regrind/PCR relationship, lot identity and substitutions requiring review | Controlled material and lot register without inferring that different grades, colors, fillers, regrind or recycled content share one drying basis |
|---|
| Material-supplier drying document and revision | Exact supplier document, revision/effective date, applicable grade/condition, stated limits, unresolved interpretation questions and approval owner | Current material-supplier record tied to the proposed grade; manufacturer examples on this page do not become project instructions |
|---|
| Incoming condition and exposure history | Packaging state, package-open time, storage/transfer exposure, incoming moisture or conditioning question, lot segregation and uncertainty requiring disposition | Dated receipt, storage and exposure record with an approved lot-disposition owner rather than an assumed dry-as-supplied condition |
|---|
| Normal, peak and changeover material demand | Normal and peak material demand basis, shot/cycle relationship, shifts, startup/changeover demand, planned future grades and the owner of every estimate | Project production basis separating estimated, calculated, quoted, observed and accepted demand without publishing a universal sizing formula |
|---|
| Proposed drying technology and package topology | Supplier-defined drying principle, central or machine-side relationship, included air-generation/bin/loading/conveying/filtering elements and unsupported alternatives | Configuration drawing and functional description for the proposed package; no technology ranking or supplier selection is made here |
|---|
| Dryer, bin/hopper capacity and residence basis | Identified dryer and bin/hopper arrangement, stated working basis, material inventory/residence assumptions, refill behaviour and uncertainty across operating states | Supplier calculation and arrangement record tied to the exact material-demand basis without a fixed capacity or residence recommendation |
|---|
| Air condition and measurement-point register | Required temperature, dew-point and airflow concepts; proposed measuring points; sensor identities; target/actual semantics; calibration status; and material-supplier approval | Project-specific approved values and instrument register; this checklist supplies no temperature, dew-point, airflow, alarm or correction value |
|---|
| Source-to-bin-to-receiver-to-feed-throat path | Controlled material route from source through the included dryer/bin and receiver/conveying elements to the machine feed throat, including isolation points and handoff owners | Reconciled flow and arrangement drawings with as-installed identities, while the wider plant material network remains separately released |
|---|
| Regrind/PCR, dust, VOC, filter and condensate disposition | Project questions for included secondary material, dust/fines, volatile matter, filters, exhaust/condensate, contamination controls, maintenance access and responsible parties | Material-, equipment- and site-specific disposition without claiming filtration, emissions, purity, recycled-material suitability or a maintenance method |
|---|
| Retained material, access, segregation and changeover | Potential retained-material locations, access points, line/bin identification, lot/color/grade segregation, change-control owner and approved procedure references | Controlled retention and segregation map; no unloading, cleaning, purging, line-clearing or changeover instruction is supplied |
|---|
| Utilities, layout, load and service-access ownership | Configuration-specific services, package loads, connection points, equipment weights, arrangement, maintenance/material access, structural responsibility and dependencies | Supplier schedules and approved site drawings without a fixed utility, mounting, foundation, connection or installation instruction |
|---|
| Residual-moisture method, sample point and lot rule | Selected method and revision, laboratory/instrument identity, sample point/time/state, lot definition, handling chain, calibration/verification, acceptance owner and result semantics | Approved method and traceable result record; ISO 15512 and ASTM D6869 titles do not prove equivalence, method selection or an achieved value |
|---|
| IMM–dryer handshake and authority split | Proposed material-available, ready, run/hold, fault, refill, restart and other required functions; source and receiver; physical/data path; authority; and safety exclusions | Approved functional and responsibility matrices without a signal order, pinout, reset action, recovery sequence or safety validation |
|---|
| EUROMAP 82.6 RC / OPC 40082-6 draft scope | Selected Release Candidate/Draft identity, proposed endpoint, common-types basis, profile/facet and conformance-unit scope, reads/writes/methods, alarms, energy, maintenance, extensions and unsupported elements | Dated applicability and support matrix that explicitly labels EUROMAP 82.6 Release Candidate 1.0.0 / Draft 01 June 2025 as non-final |
|---|
| Configured FAT/SAT, as-built and recheck evidence | Identified material, dryer/bin, conveyor and IMM configurations; approved observations; witnesses; deviations; retest; as-built records; change owners; and revalidation triggers | Signed project evidence index; unanswered capability, compatibility, value, procedure and result questions remain open |
|---|