| Project and material-supply boundary | Business decision supported, included plant area and shifts, storage-to-consumption boundary, supplier and site work, integration work and explicit exclusions | Approved scope diagram and responsibility matrix naming material owners, material-system parties, machine supplier, integrator, MES/ERP parties and site owners |
|---|
| Consuming IMM and production-cell identities | Every intended injection molding machine and cell identity, controller/application revision when known, feed-point relationship and responsible owner | Controlled machine/cell register tied to the proposed project rather than a generic machine family or unverified endpoint |
|---|
| Material, grade, lot and unit identities | Material producer, exact grade, color/additive state, approved secondary-material relationship, lot/batch identity and the units used by each record | Controlled material dictionary with source, owner, revision, alias handling and unresolved conflicts left open |
|---|
| Source silo, bin, container and bag identities | Every included source type and unique asset or location identity, current material assignment, ownership and status meaning | Approved source register and arrangement reference without implying that NEW ORIENTAL IMM supplies or controls the source equipment |
|---|
| Destination and machine feed-point identities | Every intended destination, receiver, machine feed point and intermediate handoff with its asset/location identity and responsible owner | Controlled destination register reconciled with the material-flow and cell-interface drawings |
|---|
| Loader, pipe, valve and route identities | Proposed transport elements and route segments, asset or location references, source/destination relationships and unsupported alternatives | Configuration-specific route map supplied by the responsible system party; no route is inferred from a generic topology example |
|---|
| Dryer, mixer and dosing-system relationships | Identified intermediate equipment, controller/application revisions when known, upstream/downstream relationships and separate decision-record references | Controlled equipment relationship map linking to the dedicated dryer and dosing registers without merging their settings or acceptance scope |
|---|
| Supply order and job identity/status | Required order/job identifiers, source and owner, relationship to production demand, status meanings, timestamps and missing or disputed record treatment | Approved semantic matrix and representative configured observations rather than a copied standard object model |
|---|
| Material request, reservation and availability state | Requesting and fulfilling parties, intended material/source/destination relationship, reservation and availability meanings, authority and exception ownership | Buyer-approved state and authority record with observations under the configured project; no operating sequence is supplied here |
|---|
| Planned, issued, returned and consumed quantity semantics | Which quantity states are required, source system, unit, estimate/measurement status, timestamp, rounding or uncertainty treatment and record owner | Controlled quantity dictionary and reconciliation record without a fixed quantity, tolerance, loss allowance or performance promise |
|---|
| Active route and material-path confirmation | How the current source-to-destination relationship is identified, its data or physical evidence source, status/validity semantics and confirmation owner | Configured route observation tied to the exact material, equipment identities and project conditions; no route-selection instruction is published |
|---|
| Changeover, line-clear and carryover evidence reference | Approved procedure/document references, retained-material locations, prior/current material identities, evidence owner, disposition and release status | Controlled evidence index only; the site and qualified project parties own every cleaning, line-clear, purge and changeover procedure |
|---|
| Substitution, quarantine and exception authority | Allowed and prohibited substitutions, quarantine/hold meanings, initiating and approving parties, deviation linkage and downstream notification boundary | Approved authority matrix and representative exception record without publishing automatic actions or production-release instructions |
|---|
| EUROMAP 86.1 RC applicability and extensions | Selected EUROMAP 86.1 / OPC 40086-1 / VDMA 40086-1 identity and status, related common-types basis, proposed support, exclusions and controlled extensions | Dated applicability matrix preserving Release Candidate/Draft status and separating specification concepts from actual implementation |
|---|
| Endpoint, role, access and write authority | Every proposed endpoint relationship, data direction, role, read/write/event authority, business purpose, approval prerequisite and denied function | Allowlisted responsibility and authority matrix plus configured observations; no endpoint address, credential, node map or write sequence is published |
|---|
| MES, ERP and IMM reconciliation boundary | Systems of record for material, order and machine relationships; identifiers and status mappings; ownership of conflicts, late/missing records and corrections | Approved reconciliation matrix linked to the separate IMM-to-MES contract without implying MES/ERP integration or automated traceability |
|---|
| Configured FAT/SAT evidence and deviations | Selected identity, order/status, material-path, exception, disconnect/reconnect and reconciliation observations; conditions, witnesses, deviations and retest owner | Signed configuration-specific record linked to the complete acceptance programme rather than a universal test method or procedure |
|---|
| As-built mapping, retention and revalidation | Final identities, route/equipment relationships, document and software revisions, supported/unsupported scope, retention ownership, open deviations and recheck triggers | Released as-built index and change-control record retaining superseded versions and unresolved actions |
|---|