G19
CYCLE DATA / ACCEPTANCE

Dry-cycle time alone does not establish production cycle or hourly output.

Use dry-cycle time only inside its stated comparison method, machine configuration, stroke and exclusions. Verify the target production result separately with the identified part, mold, resin, utilities, automation, quality rules and complete-cell trial.

ANSWER FIRST

One quoted time cannot answer two different test questions.

A dry-cycle result describes a defined non-production motion boundary. It does not include every stage that makes an accepted part or sustains output. Compare the dry-cycle field on its own method, then write a separate production-cycle acceptance plan.

Put both evidence objects into the acceptance matrix
Two evidence gates
  • Dry cycle: method, configuration, stroke and exclusions
  • Production: part, mold, resin and complete cell
  • Separate start/end events and measured results
  • Separate quality, output and downtime rules
  • Configuration-bound deviations and signoff
Add cycle evidence to the RFQ
TWO DIFFERENT TESTS

Basic machine motion and accepted production need separate records.

A common time unit does not make the tested scope, conditions or commercial meaning equivalent.

CHECK A / DRY CYCLE

Normalize the quoted machine-motion field.

Align the exact method and edition, clamping configuration, opening stroke, force basis, machine state, repetitions, statistic and excluded operations.

  • Useful for a like-for-like basic-motion comparison
  • Kept separate from molding and complete-cell evidence
CHECK B / PRODUCTION

Accept the configured molding cell under defined conditions.

Measure the full sequence with the identified part, mold, resin, auxiliaries, automation, utilities, quality criteria, downtime treatment and observation period.

  • Useful for the stated production job and test boundary
  • Not automatically transferable to another application
DECISION TABLE

State what each time can prove before comparing it.

Keep catalogue, configured test, production trial and accepted output as distinct evidence states.

Dry-cycle and production evidence boundaries
Evidence objectWhat it can supportWhat it cannot supportNext record to request
Quoted dry-cycle timeA comparison of basic machine or clamping-unit motion when the cited method, configuration and test conditions are alignedProduction cycle, hourly output, molded-part quality, process stability or the performance of the complete cellOriginal value and unit, method and edition, machine configuration, opening stroke, force basis, temperature state, repetitions and exclusions
Configured dry-cycle testThe recorded motion result for the identified machine state and the agreed test procedureFill, pack, cooling, plasticizing, mold release, robot takeout, inspection or downstream time that the test did not includeAs-tested identity, settings, options, software, observations, raw results, calculation, deviations and witness approval
Mold and material trialA production-cycle result for the stated mold, part, resin, cavities, process, utilities and cell scopeA different mold, resin, quality window, auxiliary package, automation sequence, site condition or production periodComplete trial conditions, cycle-stage record, quality result, downtime treatment, sample/run period and retained data
Hourly-output acceptanceObserved accepted output inside the agreed measurement boundary and quality criteriaFuture sustained output outside the test duration, staffing, scrap, maintenance, downtime and downstream boundaryStart/stop rule, accepted-part denominator, rejects, planned and unplanned stops, duration, shift conditions and signoff
CATALOGUE NORMALIZATION

Eight fields make a dry-cycle quote reviewable.

Preserve the original supplier entry. Add a normalized comparison only after the source basis is visible.

Dry-cycle RFQ fields and comparison reasons
FieldRecordWhy it controls the comparison
Method identityExact recommendation, edition or supplier procedure used; do not accept an unlabeled catalogue field as a common basisDifferent definitions can include or exclude different motions, force application, waiting periods and reporting rules
Machine configurationMachine, clamping unit, drive variant, options, software and any setting or equipment that changes the motion sequenceA family name does not identify the as-quoted or as-tested mechanism and control state
Opening-stroke basisTest stroke, measurement datums and relationship to the applicable method or quoted machine dataA shorter or otherwise different travel cannot be compared as though the motion distance were identical
Clamp-force basisForce application required by the cited method, plus any included build-up, locking, release or waiting treatmentThe clamp sequence and time boundary must match before two results describe the same test
Machine stateTemperature or ready state, utilities, lubrication condition, warm-up rule and the start condition used for measurementA cold, warmed or differently supplied machine can create a different comparison boundary
Repetitions and resultNumber of successive cycles, raw observations, reported statistic, precision and any excluded or interrupted runOne isolated movement or a rounded headline does not show how the stated result was produced
Included and excluded operationsInjection, plasticizing, filling, cooling, ejection, cores, mold protection, robot and waiting states explicitly marked in or outAn operation outside the dry-cycle boundary can still control the production cycle
Evidence statusCatalogue, calculated, simulated, measured, witnessed or contractually accepted status with source, revision and ownerA quoted field and an as-tested result are different evidence states
PRODUCTION ACCEPTANCE

A complete-cell trial needs its own controlled boundary.

These are procurement fields, not a universal operating or test procedure. The responsible parties must approve the actual method.

Complete-cell production acceptance fields
Trial fieldRecord before acceptance
Production identityPart and drawing revision, mold and cavities, runner, resin grade/condition, color/additives and accepted quality criteria.
Configured cellMachine, injection unit, screw, options, software, mold-temperature control, cooling, dryer, robot, inspection and downstream equipment.
Cycle stagesFill, transfer, pack/hold, cooling, plasticizing, mold motion, cores, ejection, takeout, inspection, reject and downstream handoff.
Utilities and readinessPower, cooling-water and air conditions, ambient state, material/mold conditioning, warm-up and stable-start rule.
Measurement boundaryCycle start/end event, run duration, sampling, accepted-part denominator, planned/unplanned stops and data source.
Quality and outputInspection method, sample plan, reject treatment, accepted output calculation and the rule for interrupted or unstable periods.
ResponsibilitiesSupplier, buyer, mold, material, robot, auxiliary and site duties for preparation, witnessing, data, retest and signoff.
Deviation controlActual condition, requirement affected, containment, owner, due date, retest method and retained closure evidence.
ACCEPTANCE SEQUENCE

Move from a quoted field to a bounded production result.

The sequence prevents a basic-motion figure from becoming an unsupported capacity promise.

01

Normalize the quoted field

Keep the original dry-cycle value and unit, then attach its method, edition, configuration, stroke, force basis, machine state and exclusions. Do not rank an unlabeled value.

02

Separate motion from molding

List every production operation absent from the dry-cycle boundary, including filling, plasticizing, cooling, mold functions, ejection, takeout and downstream handling.

03

Define the complete-cell trial

Freeze the part, mold, resin, cavities, configured machine, auxiliaries, automation, utilities, start condition, duration and quality method before setting a production-cycle acceptance rule.

04

Measure the requested outcome

Use the agreed cycle event, accepted-part denominator, downtime treatment, sampling and data source. Keep dry-cycle and production-cycle results in separate fields.

05

Close deviations without extrapolation

Record every difference from the agreed test condition, decide whether retest is required and limit the accepted result to the configuration and boundary actually observed.

PRIMARY SOURCES / BOUNDARY

Official sources define the field and method—not this site's machine performance.

EUROMAP 6 supplies the comparison-method boundary; EUROMAP 102 Draft 1.0 (January 2026) supplies a draft technical-data definition; the ARBURG sheet is a named OEM catalogue example. None verifies a NEW ORIENTAL IMM result.

EUROMAP

EUROMAP 6 Version 2.0 — Determination of the Duration of the Dry Cycle

The official recommendation defines a comparison test for the clamping-unit dry cycle without injection or plasticizing. It specifies the test-block, stroke, force-application, working-temperature, successive-cycle and reporting basis.

Boundary: The method does not establish a production cycle, hourly output, molded-part quality or complete-cell result. A result still needs the exact machine configuration, method edition and as-tested record.

EUROMAP

EUROMAP 102 Draft 1.0 (January 2026) — Technical Data for Injection Molding Machines

The official draft identifies DryCycleTime as a measure of basic machine speed and states that it includes cycle operations except plasticizing, mold filling and cooling of the molded part. Its references include EUROMAP 6.

Boundary: This is Draft 1.0, not a final published standard, production acceptance method or supplier capability record. The draft status and January 2026 edition must remain visible wherever it is used.

ARBURG

ALLROUNDER 520 A Multi-Component Technical Data

This official product-specific sheet shows dry-cycle time as a separate EUROMAP-labelled technical field associated with a stated opening stroke and identified equipment variants.

Boundary: Its values, equipment and disclaimers belong only to the named ARBURG technical sheet. No value or capability is transferred to NEW ORIENTAL IMM or generalized to another machine.

BUYER QUESTIONS

Dry-cycle and production-cycle acceptance FAQ

These answers keep a catalogue comparison method, a configured machine test and a complete-cell production result in separate evidence states.

01Can quoted injection molding machine dry-cycle time by itself establish production cycle or hourly output?

Not by itself. Dry-cycle evidence can compare basic machine or clamping motion only inside an aligned method and configuration. Production also includes the mold, resin, injection, packing, cooling, plasticizing, ejection, automation, inspection and downstream boundary. Verify production cycle and accepted output in a separately defined complete-cell trial.

02What must match before two dry-cycle values are compared?

Match the method and edition, machine and clamping configuration, drive/options/software, opening stroke, force-application basis, temperature or ready state, repetitions, reported statistic and included or excluded operations. Flag every difference instead of forcing a ranking.

03What does EUROMAP 6 cover?

EUROMAP 6 provides a comparison method for the duration of the clamping-unit dry cycle without injection or plasticizing. Use the official document for its exact test block, stroke, force, temperature, repetition and reporting requirements. It is not a complete production-cycle or output test.

04Is EUROMAP 102 a final standard?

The source used here is EUROMAP 102 Draft 1.0 dated January 2026. It is used only to explain the draft DryCycleTime data field and its exclusions. It must not be presented as a final release, certification, supplier conformity or production result.

05What should a production-cycle acceptance trial include?

Identify the part, mold, cavities, resin, configured machine and complete cell; define utilities, conditioning and start state; map every cycle stage; set the measurement period, downtime and reject treatment; and agree the quality, evidence, witness, deviation and retest rules.

06What should be added to the RFQ?

Request the original dry-cycle value with its method, edition, configuration, stroke, force basis, machine state, repetitions and exclusions. Keep the target production cycle and output in a separate section with the complete-cell trial conditions and acceptance plan.

CYCLE EVIDENCE / NEXT STEP

Request two records: the dry-cycle basis and the production trial.

Attach the quoted field, method, edition, configuration, stroke, force basis, machine state, repetitions and exclusions; then define the part, mold, resin, complete cell, measurement boundary, quality criteria and deviation process separately.